With specific ‘close control’ of the room acoustics as well as temperature and humidity required, we constructed the room modules around a structural steel frame to support all plant and services directly above.
Project Type : ISO 5 & 7 Cleanroom Facility
Size : 49m2
Duration : 5 weeks
Cost : £93,000
We received an order from ISDI London, in July, to design and build a temperature-controlled ISO 5 & 7 Cleanroom Facility. Work commenced at the end of the month and completed on time, in September.
We delivered this project on a turnkey, design and build basis. All necessary fit-out, including mechanical services, electrical & data, compressed air & vacuum, lighting, flooring, furniture, waste management and clean down were included.
With specific ‘close control’ of the room acoustics as well as temperature and humidity required, we constructed the room modules around a structural steel frame to support all plant and services directly above.