Project Type : ISO 5 & 7 Cleanroom Facility Size : 49m2 Duration : 5 weeks Cost : £93,000
Who we worked with
We received an order from ISDI London, in July, to design and build a temperature-controlled ISO 5 & 7 Cleanroom Facility. Work commenced at the end of the month and completed on time, in September.
Who we worked with
We delivered this project on a turnkey, design and build basis. All necessary fit-out, including mechanical services, electrical & data, compressed air & vacuum, lighting, flooring, furniture, waste management and clean down were included.
How we did it
With specific ‘close control’ of the room acoustics as well as temperature and humidity required, we constructed the room modules around a structural steel frame to support all plant and services directly above.