implant

Through competitive tendering and negotiation CDCfm was engaged as specialist contracting partner of choice to this global medical device manufacturing group.

Following extensive dialogue to fully scope and agree exact client preferences for specification our in-house project teams were challenged to provide ultra-fast completion to meet demanding client manufacturing commitments. This full refurbishment project challenged CDCfm to design, construct and validate over 600m² of multi-suite ISO 7 and ISO 8 cleanroom facilities

Who we worked with

Project Type : Implant

Size : 600m2

Duration : 18weeks

Cost : £680,000

What we did

How we did it

The facility refurbishment began with the partial strip out of the existing building. Extensive use of full height glazing within the composite panel wall structure together with walk-on access ceilings, vinyl floors and high specification doors complimented the overall facility architecture. The provision of new HVAC to environmentally condition the areas together with dedicated process gases and cooling water along with all key electrical services including lighting, equipment and general power supplies were provided.

Through professional collaborative working CDCfm’s design and project management team exceeded all expectations ensuring the site remains a centre of manufacturing excellence within the group.